KIAN has been contracted by the USACE, Omaha District to conduct a site investigation (SI) at the Former Weingarten Prisoner of War (POW) Camp, specifically focusing on the historical use of two small arms firing ranges. This investigation includes surface soil sampling, near-surface soil sampling, surface water, sediment, and background sampling to assess the potential presence or absence of munitions constituents (MC) associated with past military training activities.

Located approximately 60 miles south of St. Louis, Missouri, the site has transitioned from its original military use site to its current state as agricultural, grazing, and timber use. Following its operation during World War II returned to private ownership in 1949. Throughout the course of this project, KIAN prides themselves on communicating and coordinating with the current landowner throughout sampling operations.

KIAN has successfully completed and received approval for a range of essential project management documents, including but not limited to the Project Management Plan (PMP), Quality Assurance Project Plan (QASP), and the Uniform Federal Policy for Quality Assurance Project Plan (UFP-QAPP), ensuring adherence to stringent environmental regulations such as the Military Munitions Response Program (MMRP) and the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).

The investigation aims to elucidate the potential fate and transport of chemicals of potential concern (COPC) released into the environment, while assessing current and future human and ecological receptors. A conceptual site model (CSM) has been developed to visualize these interactions, indicating that potential exposure pathways remain relevant for ongoing and future land use scenarios.

Through this rigorous assessment, KIAN is committed to ensuring environmental safety and compliance with all applicable Department of Defense requirements, laying the groundwork for future land stewardship in this historically significant area.

Related Projects

Whiteman Air Force Base Site Inspection Sampling

KIAN successfully completed a Comprehensive Site Evaluation (CSE), Phase II, at the former small arms range located at Whiteman Air Force Base. Constructed in 1942 and operational until 1990, this evaluation was part of the Military Munition Response Program (MMRP) to assess potential environmental impacts from historical military activities.

Lonestar

Work included design-building:
Planning documents (APP, ESS, Work Plan, design drawings), One-Call, MEC/UXO clearance, blast resistant building, electrical, plumbing, HVAC, site work, ADA ramp, ADA parking and sidewalk, EV charging station, sanitary sewer, septic tank inspection and cleaning, tree removal, grading, parking, mechanical gate with solar panels, repair and replace deteriorated waterline, etc. The project also includes 24 months of maintenance and janitorial support of all facilities.